Forensic Planner / Delay Analyst, DGA (UK) Ltd, Multiple clients

START Date: 
March, 2008
END Date: 
April, 2011

 

Forensic Planner

Providing forensic planning support for multiple clients in rail, civil and building projects in support & defence of claims for time and quantum including;


- Analysis on behalf of contractor in major central London rail infrastructure project.


- Delay analysis for major signalling upgrade project under London Underground PPP contract.


- Programme analysis and report response to EOT claim, advice on contract baseline programme for superintendent of station redevelopment in central Birmingham.


- Analysis and support advice on contractor time for Hotel developer’s new development in London’s West End.


- Construction of detailed as-built programme for defence of contractor claim in central London rail bridge replacement project.