PROJECT ENGINEER, PHILIPPINE NATIONAL OIL COMPANY - ENERGY RESEARCH & DEVELOPMENT, EXPERIMENTAL WORK FOR CHARCOAL OIL MIXTURES PROJECT

START Date: 
November, 1990
END Date: 
May, 1991

• Responsible for preparation of process flow of the system on the initial project conceptual designs and performs its technical

supervision on fabrication, installation, & modification of equipment's plan and specification.

• Responsible for supervision of direct procurement of equipment's & parts, materials and other necessary consumable items

necessary for the project.

• Responsible for supervision of repairs, maintenance and op’ns of fire-tube boiler and other equipment as required on the project.

• Responsible for supervision in the developing and formulating of technical procedures of data gathering necessary for project

evaluation, analysis and recommendation.

• Responsible for technical supervision on blending percentage of mixtures solution through transducer including coal ash analysis

ratio and gather its data of information for laboratory analysis.

• Responsible for review, analysis and evaluation of all the data’s obtained in preparation of project reports.

• Performs other task s relevant to its timely implementation, commissioning and accomplishment of the project.