Engineering Planner, GE Oil & Gas, Subsea Trees

START Date: 
October, 2010

Summary of my responsibilities are:

 

  • Construct and manage detailed planning schedules, utilizing Primavera P6 software, that represent activities required to successfully deliver key project / scheme milestones;
  • Developplans to sufficient detail to ensure effective control of all project deliverables.
  • Identifycritical activities and continuously monitor and report to project manager
  • Generateproject reports that reflect the actual project status both with respect to time and performance
  • Ensure planning and reporting requirements are included in all Subcontracts and Purchase Orders
  • Manage and integrate Variation orders time impact in the project plan
  • Describe the planning process for any product delivery projects
  • Collect technical documentation in order to understand the project deliverables and all components
  • Define sufficiently detailed logical network to define need dates for all materials and components.
  • Together with procurement department develop a complete procurement plan including all components defined in the scope of supply list.
  • Create Engineering Plan with milestones for design freeze and placement of Purchase orders
  • Fully resource loadproject plans to include man-hour estimates to reflect need for engineering resources.
  • Update integrated plan with engineering and procurement activities to enable effective analysis of the plan.
  • collect reports from the Engineering and Procurement Department and report deviations
  • Monitor sub-contractors plans and analyze and report deviations.
  • Provideschedule input to Variation Orders and define/analyze cumulated effect on overall project.
  • Prepare weekly and monthly reports as required.