Engineering Planner, GE Oil & Gas, Subsea Trees
START Date:
October, 2010 Summary of my responsibilities are:
- Construct and manage detailed planning schedules, utilizing Primavera P6 software, that represent activities required to successfully deliver key project / scheme milestones;
- Developplans to sufficient detail to ensure effective control of all project deliverables.
- Identifycritical activities and continuously monitor and report to project manager
- Generateproject reports that reflect the actual project status both with respect to time and performance
- Ensure planning and reporting requirements are included in all Subcontracts and Purchase Orders
- Manage and integrate Variation orders time impact in the project plan
- Describe the planning process for any product delivery projects
- Collect technical documentation in order to understand the project deliverables and all components
- Define sufficiently detailed logical network to define need dates for all materials and components.
- Together with procurement department develop a complete procurement plan including all components defined in the scope of supply list.
- Create Engineering Plan with milestones for design freeze and placement of Purchase orders
- Fully resource loadproject plans to include man-hour estimates to reflect need for engineering resources.
- Update integrated plan with engineering and procurement activities to enable effective analysis of the plan.
- collect reports from the Engineering and Procurement Department and report deviations
- Monitor sub-contractors plans and analyze and report deviations.
- Provideschedule input to Variation Orders and define/analyze cumulated effect on overall project.
- Prepare weekly and monthly reports as required.