Planning/ Scheduling Manager, KBR, All listed
START Date:
April, 2003 More than 20 years of experience in Primavera P3/ P6/ P7 planning and scheduling, project management, progress measurement in oil & gas industries. Professional experiences includes LNG Plants (construction/ pre-commissioning/ commissioning/ live plant environment & re-build), Petrochemical Plants, Refineries, Ethylene Plant, Oil & Gas Plants, Power Plants, Gas Turbine Power Plant, Steam Turbine Power Plant, Light Rail Transport, Highway and Paving, Storm Water Drainage.
Has worked in Malaysia/ Hong Kong/ China/ Karratha Australia/ Skikda Algeria/ Qatar/ Yemen/ Perth Australia
Has worked in below listed LNG projects, as lead/ department lead/ manager/ senior manager roles,
- MLNG 3, Bintulu, Malaysia (Train 7 & 8)
- MLNG 1 & 2, Bintulu, Malaysia
- Woodside Northwest Shelf LNG 4 Expansion, Karratha, Australia (Train 4)
- Sonatrach Unit 10 Re-Start GL-1/K, Skikda, Algeria
- Qatargas-II, Ras Laffan, Qatar (Train 4 & 5)
- Yemgas, Bal-Haf, Yemen (Train 1 & 2)
- New LNG Train, Skikda, Algeria
- Greate Gorgon LNG, Perth, Australia (Train 1/2/3)
- Company:
- Industry:
- Job Role:
- Project:
- Region: