PLANNING ENGINEER, BIZVILLE PROJECT MANAGEMENT, De-Bottlenecking Project For Energia/Oando Ebendo Marginal Oilfield (Client: Exxon Mobil)

START Date: 
September, 2012
END Date: 
May, 2015

*Create new Schedule/Plan by importing Project Plan to Primavera & Ms Project 
*Create/Modify WBS and Add Activity in Primavera/Ms Project.
*Assign Labour, Non-Labour and Material Resources to Activities.
*Develop Project Schedule/Plan in Primavera & Ms Project.
*Analyse labour resources for resource over allocation.
*Update Project Status based on the organizational project control policy
*Track and monitor closely the critical activities and draw attention of team members and sub-contractors to them. 
*Display, analyse and interpret Earned Value Metric Table; Budget & Forecast 
*Develop and Analyse man-hour based S-curve and cost based S-curve in Ms Excel for growth, slippage and project duration forecast. 
*Develop and Prepare periodic schedule progress reports and look-ahead reports in Primavera, Ms Project & Excel

Experience Hours (Planning & Scheduling): 
3500
Experience Hours (Cost Management): 
3500