Site Q.S./Planner, Tyco International Thailand Ltd., Peninsula Hotel, GSS Array, Golden Food Products,for Liebherr Factory
START Date:
March, 1995
END Date:
February, 2000 Site based Q.S,
Total re-measurement of M&E works for Peninsula Hotel project value at 1.2 Billion Baht. Reconciled measured quantities with James R. Knowles QS representatives.
Valuation of M&E work worth 180 Million THB contract value for GSS Array technology. Evaluation two sub contractors’ monthly billing and change orders.
Valuating of M&E works for Golden Food contract value 60 Million baht THB.
Valuation of M&E work for Liebherr Factory contract value 34 million baht THB.
Total man hours for all above projects approximately 800,000 man hours
Experience Hours (Planning & Scheduling):
5800
Experience Hours (Cost Management):
8750
Experience Hours (Forensic Analysis):
1400 - Company: