Project Planner , London Underground Limited, Northern Line Upgrade Project

START Date: 
August, 2001
END Date: 
January, 2002

Project Planner on a Private Finance Project to install Power Quality Equipment to the value of £65 Million for London Underground Limited (LUL) as part of a variance to the Northern Line Upgrade project.

  • Develop from the contractual programme a working level 4 programme for the civil, equipment installation, cable installation and pre-commissioning work (Static Var Compensators, Harmonic Filters, Unisafe 22kV Switchgear) at 7 bulk load sites around the LUL rail network.
  • Liaise with ABB Sweden, Alfreton, and Ellesmere Port on the delivery and Factory Acceptance Test dates.
  • Weekly site visits to review and collaborate progress and attend site vendor meetings.
  • Produce progress reports to the client as per period payment profiles.
  • At completion of installation stage, project planning handed over to Northern Line Planner for commissioning completion.