Project Planning Coordinator, SMS Demag Ltda., Steel making projects: bloom and beam blank continuous casting machine, steel plant and steel process plants.

START Date: 
January, 2000
END Date: 
June, 2007

Planning management to install the CSN-PR plant during 4 years, working as user with the software Primavera including the schedule development and its control, and the Converter 3 plant to CST during 3 years. Both projects were turnkey contracts, comprising from engineering to commissioning phase. The project language was English and the participation started on the late negotiation phase. Support to preparation and defense of claims associated to both projects. Commissioning planning of the bloom continuous casting machine to Açominas.

05.2007 – 06.2007    commissioning planning of the bloom and beam blank continuous casting machine supplied to Açominas in Ouro Branco-MG.

05.2004 – 04.2007      planning management of the turnkey contract, comprising from engineering to commissioning phase, to supply the Converter 3 plant to CST in Vitória - ES. Member of the leadership team a consortium of 7 companies from 2 countries (Brazil and Germany). The project language was English. Support to defense of claims associated to the contract.

01.2000 – 04.2004      planning management of the turnkey contract, comprising from engineering to commissioning phase, to supply a process plant with galvanizing, coating and pickling lines; rolling mill; roll shop; acid regeneration, water treatment, substation and others facilities, starting up the CSN-PR in Araucária. Member of the leadership team a consortium of 11 companies from 4 countries (Brazil, Germany, U.S.A. and Canada). The project language was English and the participation started on the late negotiation phase. Support to preparation of claims associated to the contract. Work as user with the software Primavera including the schedule development and its control. Anticipation from 5 to 42 days in the contractual terms.