PLANNING ENGINEER, Thiess Industrial Projects, Wandoan Coal Handling & Preparation Plant - Wandoan Coal Project
START Date:
November, 2011
END Date:
January, 2012 - Prepare resource & cost loaded loaded schedules for Process Plants in Coal Handling Sector
- Effectively gather construction progress activity to provide advice and feedback to construction personnel on their work area activities monitored against the Construction Program.
- Interface with construction personnel providing feedback on progress impacts on the Construction Program.
- Interface with construction personnel on productivity.
- Continual maintenance of the Construction Program through analysis of construction activity data and effective update of program using project software.
- Provision of progress reports for presentation to the Project Management Team.
- Liaise with construction personnel on site to ensure that all construction activity data reflects real levels of progress.
Experience Hours (Planning & Scheduling):
500 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: