Planning Engineer, Rotary Engineering Limited, Evonik Me6 Project, Proposed Petroleum Storage & Handling Facilities for Jurong Port Terminals (Phase 1), SRC Mogas Cogen Project, Afton LION Project

START Date: 
May, 2015
END Date: 
September, 2018
  • Develop and update project schedule using Primavera P6 during tender and execution phase
  • Prepare budgeted manpower and resource plan required for project completion
  • Prepare forecast schedule to consider variation/deviation from original schedule
  • Schedule Turn Around work aligned with other construction disciplines
  • Monitor and provide current achieved progress with Curves and Gantt Chart
  • Determine critical issues or bottle neck for identification of potential delay
  • Track material deliveries, including free-issued and long-lead items
  • Produce and monitor schedule-related KPI
  • Establish database/tracker used for updating balance of works
  • Provide system completion plan
  • Prepare Monthly Progress Claim with supporting documents
  • Assist Project Manager in preparing/monitoring of Project Budget and commitment report
Experience Hours (Planning & Scheduling): 
6800