Senior Planner, Petrojet, Petrochemical Projects

START Date: 
October, 2010

SHERIF GABER IBRAHIM

PERSONAL DATA

Name             : Sherif Gaber Ibrahim Ahmed.

Address          :Sumed Building No. 2, Smoha, Alexandria, Egypt.

Telephone       : (0020-03) 3870076 – 5428909 (Alexandria).

Mobile            : 0125338752-0123318060.

Email             : Sherifgaber@yahoo.com.

Nationality      : Egyptian.

Date Of Birth   : 1974 – Alexandria.

Languages      : Arabic and English.

Marital Status  : Married.

Military Status: Exempted.

  OBJECTIVE

 

Successful Civil Engineer with over 12 Years experience of project controls, contract administration and quantity surveying in Major Construction Projects seeking an employment opportunity in fields of Project Controls (Planning, Scheduling &Technical Office)

  QUALIFICATIONS

 

  • B.Sc, Civil Engineering, Faculty of Engineering-Alexandria
  • Diploma in Construction Management, Faculty of Engineering-Alexandria
  • Diploma in Construction Engineering & Project Management, Arab Academy forScienceandTechnology.
  • Member, International Project Management Association(IPMA), titled as Certified Project Manager (Level C).
  • Member, Egyptian Syndicate of Engineers.
  • Project Cost Control course from The American University.
TECHNICAL SKILLS

 

  • Comprehensive knowledge of Project Controls work processes including Planning and Scheduling.
  • Constructing work break down structure andorganization charts.
  • Using primavera for organizing and planning projects including formation of all resource plans andupdating all activities progresses, analyzing variances to give corrective actions.
  • Calculating required resources & formation of internal budgets
  • Project managementcorrespondence control, attending progress and management meetings with the Client, holding meetings internally and with sub-contractors.
  • Progressreportingandperformance analysis reports, also responsible for contract administration, claims and Quantity Surveying.
COMPUTER SKILLS
  • Use spreadsheets for Projects Budgets, Estimating Project resources, Monitoring & Evaluating Project Progress, Reporting of Project Status including Progress, Quantities, Productivity, manpower & Equipment, Civil Works Quantity Surveying.
  • Very good knowledge of Primavera for scheduling and MS office.
Project Highlights

 

       Maximization of C2& C3 Project

Duration              : May 2006 till now.

Company            : PETROJET(The Petroleum Projects & Consultation Company)


 

Project Type        : Gas Plant.


 

Project Budget     : 65 million US$.


 

Client                  : GASCO.


 

Location              : Alexandria, Egypt.


 

Scope of work      : Scope of work includes the following:

  • W.P.1  Rough Grading & Pilling Works & Site Development
  • W.P.2  Storage Tanks & Spheres
  • W.P.3  Temporary Construction Facilities, Fencing & Mobilization
  • W.P.4  Civil Works & Buildings
  • W.P.5  Steel Structures
  • W.P.6  Mechanical Works (Piping & Equipments)
  • W.P.7  Electrical and Instrumentation


 

Position               : Senior Planning Engineer.

Rehabilitation of Sewer and Water network Project

Duration              : September 2005 to May 2006.

Company            : PETROJET(The Petroleum Projects & Consultation Company)

 

Project Type        : Urban Project.


 

Project Budget     : 13 million euro.

Client                  : Taiz Water and Sanitation local Corporation.

Location              : Taiz, Yemen.


 

Scope of work      : Scope of work includes the following:

  • Rehabilitation of 400 Km of water network
  • Rehabilitation of 70 Km of Sewer network

Position               : Senior Planning Engineer.

 

Egyptian Linear Alkyl Benzene Project


 

Duration              : October 2004 – September 2005

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Petrochemical Plant.


 

Project Budget     : 7 million US$.


 

Client                  : Egyptian Liner Alkyl Benzene Company.


 

Location              : Alexandria, Egypt.


 

Scope of work      : Scope of work includes the following:

  • Site preparation and backfilling (200000 Cubic meter)
  • Execution of deep foundation (450 pile)
  • Execution of site fencing (2 K.M)


 

Position               : Senior Planning Engineer.

 

Egyptian Liquefied Natural Gas Project

Duration              : February 2003 – October 2004

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : L.N.G Plant.


 

Project Budget     : 20 million US$.


 

Client                  : El Behara LNG Company.


 

Location              : Edko, Egypt.


 

Scope of work      : Construction of Marine Jetty (2.5 Km) for LNG exportation:

  • Fabrication of 3000 ton steel trestle.
  • Fabrication of 16000 ml steel piles.
  • Erecting of 1250 ml Steel piles.
  • Erecting of 450 ml of Steel trestle
  • Erecting of 7.5 km cable tray
  • Welding and erecting of 60000 Din Stainless steel, carbon

pipe with a total length of 20 km

  • Casting of 65000 m3 concrete for sea defense
  • Casting of 10000 m3 concrete for trestle slabs and piles heads

Position               : Senior Planning Engineer.

 

Development of Ministry Council in Alexandria Project

Duration              : May 2002 – February 2003

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Urban Project.


 

Project Budget     : 3 million US$.


 

Client                  : Ministry of Petroleum.


 

Location              : Alexandria, Egypt.


 

Scope of work      : Internal finishing works (Civil-Sanitary-Electrical-HVAC) &

                             Landscape work

Position               : Planner -Technical office engineer.

 

Feed Study For L.N.G Project in Edko

Duration              : December 2001 – May 2002

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Technical study Project.


 

Project Budget     : 100 thousand US$.


 

Client                  : Bechtel.


 

Location              : Edko, Egypt.


 

Scope of work      : Providing feed study including the following:

  • Water Supply feed study
  • Transporting method for heavy equipments
  • Dredging method for Project Jetty
  • Site preparation (studies on suitable Crushers &Quarries)

Position               : Technical office engineer

 

       Construction of EPC Hospital

 

Duration              : March 2000 – December 2001

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Urban Project.


 

Project Budget     : 2 milloin US$.


 

Client                  : Ministry of Petroleum.


 

Location              : Alexandria, Egypt.


 

Scope of work      : Scope of work includes the following:

  • Execution of Deep foundations (pilling works)
  • Construction of concrete skeleton
  • Finishing works

Position               : Planning, Technical office and Site engineer

 

 Rashpetco Gas plant

 

Duration              : November 1999 – March 2000

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Urban Project.


 

Project Budget     : 1 milloin US$.


 

Client                  : Rashpetco Company.


 

Location              : Edko, Egypt.


 

Scope of work      : Scope of work includes the following:

  • Construction of Staff accommodation buildings
  • Construction of administrating building.
  • Construction of company mosque.

Position               : Planning engineer

 

Construction of WEPCO new Administration Building

 

Duration              : December 1997 – November 1999

Company            : PETROJET(The Petroleum Projects & Consultation Company)

Project Type        : Urban Project.


 

Project Budget     : 6 milloin US$.


 

Client                  : WEPCO Company.


 

Location              : Alexandria, Egypt.


 

Scope of work      : Scope of work includes the following:

  • Execution of deep foundation (900 Pile).
  • Construction of the building concrete Skelton (12000 m3).

Position               : Planning & technical office engineer