Assistant Manager - Project Controls, Newfields, Buritica Mining Project
START Date:
August, 2018
END Date:
June, 2020 Project Controls Consultant
Elaborate a new baseline of the project master schedule loaded with resources.
Create the system to use to manage and control the project according to the Definitive Estimate approval.
Maintain oversight of the projects KPIs.
Assess in the selection/evaluation of construction contractors through the project’s life.
Report to the board about the status of the project (plan, costs, risks, change orders, deviations to scope).
Experience Hours (Planning & Scheduling):
2500
Experience Hours (Cost Management):
1600
Experience Hours (Forensic Analysis):
650 - Company: