Project Planning Engineer, USTAY Construction, Polypropylene and High Density Polyethylene Plant Project
START Date:
December, 2016
END Date:
September, 2017 USTAY Construction from: 26 December 2016 up to 30 September 2017
Position: Project Planning Engineer
Project involved:
- SOCAR PP-U&O and HDPE Projects
Polypropylene and High Density Polyethylene Plant Project.
- Polymerization Area
- Polymerization Building.
- Polymerization Piperack.
- Raw Material Handling.
- Low Pressure Solvent Recovery.
- Steam Condensate.
- Ethylene Treatment.
- Cooling Water Supply Return.
- Solvent Branch Piperack.
- Solvent Recovery Piperack
- Ethylene Compressor
- Flair Drum
- Reactor Dump Tank
- Powder Conveying Package
- Nitrogen Purification Package
- Interconnection Piperack Between Extrusion & Polymerization Piperacks.
- Extrusion Area
- Extrusion Building.
- Extrusion Piperack.
- Additive Storage.
- Tower Crane.
- Polymer Water Pit.
- Organoleptic Area
- Organoleptic Building.
- Organoleptic Treatment
- Blending Silo are
- Blending Silo Building.
- Pellet Conveying Package.
- Blending Silo Piperack.
- Bagging & Packing Silo Area
- Bagging & Packing Building.
- Bagging Silo Piperack.
- Fire Water Valve House Area
- Fire Water Valve House Building.
- Fire Water Valve House Piperack.
- UG Lines
- Substation Area
- Substation Building.
- Control Room
- Rack Room
- Transformer
- Substation Piperack
- Catalyst Unloading Building
- Catalyst Activator Building
- Cooling Tower
Job Description:
- Management / Construction plans at all levels
- Plan, Report and control work schedule.
- Weekly reporting of the work progress in accordance to the plan package i.e Plan against actual and its variances
- Early warning of foreseeing area of concern to Project manager of any issue causing delay to the project
- Critical path program analysis
- Weekly, Monthly and periodic 90 days Plan of Construction
- Checking Daily Man Power and preparation of the daily report
- Make a plan in P6 at all levels also in MS Project
- Hard working under pressure with Planning team
- Checking Construction Progress on a site
- Updating schedule P6
- Daily , weekly Photo Progress
- Milestones Plan
- Project Summary Schedules
- Project Detailed Schedule
- Baseline Schedule
- Progress S-Curves
- Updating Layouts
- 90 Day Plan
- Making Progress Payment
- Quantity Surveying.
- Steel Structure progress and making databases.
- Pipe Racks progress calculations.
- Piping prefabrication and erection works (shop weld, field weld, tack weld etc.) progress calculations.
- Spooling works calculations from isometrics.
- Making concrete data bases for actual and for drawing quantities and keeping under control for different of both.
- Preparing equipment’s transporting and installation schedule for purchase.
- Preparing schedule for electrical, earthing and finishing works and given progress.
- Making micro schedule for critical works.
- Calculating Underground works progress by quantities from drawings and given progress.
- Making schedule and progress for Piping prefabrication, fabrication, site assembly and site erection works. Also for support fabrication and erection works.
- Weekly & Monthly Achieved and Against progress calculation & Preparing 28 days look ahead schedule for below works
- Civil Works
- Piling, Excavation, Foundation, Backfilling, Cast In Situ R.C. Structure, Building – Masonry, Paving – Concrete, Building – Finishing, Grouting - Steel Structures, Steel Sheets (Roofs / Sidings), Fire Proofing Steel Structure, Clean Agent System Installation, HVAC installation, UG Sys. - Pit/Trench/Pipe/Cable (UG), UG Sys. -Storm Water Drain(UG), UG Sys. - RC/HDPE/PVC/PP Lines (UG), UG Sys. - Earthing System - Strip Laying (UG) Works.
- Steel Structure Works.
- Steel Structure Assembly & Erection, Sec. Steel/Handrails/Ladders/Gratings Works.
- Piping Works.
- Piping - Sandblasting. & Primer, On Site Erection Piping >=2, On Site Support Erection, On Site Erection Piping <2, On Site Support Fabrication, Tie-Ins Works.
- Mechanical Works.
- Package Units, Heat Exchangers, ROTARY COMPRESSORS,VESSELS / SILOS, AUXILIARY STEEL STRUCTURE, Other Static Equipment’s, Loop Reactors, Extruder, Package Units-Pneumatic Conveying System - Equipment, Package Units - Pneumatic Conveying System - Pneumatic Haulage Piping, Static - Columns, Other Machinery Works.
- Electrical Works.
- Field Panels/Local Stations , Heating System, Lighting Systems, Substation Equipment (Common-60, HDPE-106nos.), Cathodic Protection Electrical work(UG), Distribution Transformer
- Instrumentation Works.
- Branch Cable Tray, Cabinets/J. B/L/P/Shelters, Main Cable Laying, Main Cable - Terminations, Branch Cable Laying & Termination, Instruments - Installation , Instruments - Calibration, Connections
- Painting & Insulation Works.
- Piping Painting Finishing Coats, Steel Structure & Piping Supports-Finishing Coats, Equipment Painting Finishing Coats, Insulation - Piping, Insulation – Equipment
- Pre-commissioning
- Pre-commissioning Activities
Experience Hours (Planning & Scheduling):
1450 - Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: