Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Planner, O'Donnell Griffin, All Great Western Region Projects

START Date: 
January, 2012
END Date: 
May, 2012

O’DONNELL GRIFFIN:   Senior Project Planner/Asst PM – Brockman 4 Phase 2 Expansion Project (FIFO) – project upwards of AUD$20mm

 

  • Develop Primavera P6 plan to encompass all possible variations for the B4P2 mine expansion project for the installation of E,I&C systems.
  • Introduced new integrated system for Cost & Resource tracking to report out of P6 into ODG’s system.
  • Provide resource and cost/budget systems in both Primavera & Excel.
  • Manage forensic analysiswith SMP Contractorand work-face access requirements to prepare EoT’s & delay claims.
  • Manage the plan through the procurement, mobilization & project execution phases.
  • Report through to the Client as well as Head Office through standard procedures such as Performance Curves, Resource Productivity analysis, cost/budget analysis, EoT Claims/Process, etc.
  • Develop a system to manage the Work Packs for each Team and Work Area which could be quantified and measured to meet both ODG internal systems and Client requirements.
  • Acting Project Manager in Project Manager’s absence.
Experience Hours (Planning & Scheduling): 
900
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
250