Various, Sasol, Sasol III Secunda

START Date: 
July, 1994
END Date: 
January, 1996

 

COMPANY:        L & C STEINMÜLLER CONSTRUCTION                 DUR:                NOV 95 TO JAN 96

POSITION:        SITE PLANNER *                                                CLIENT:            SASOL

PROJECT:          ACN RELOCATION PROJECT SASOL III SECUNDA

Measuring overall site progress by system, area and priority. Issuing of site instructions to sub-contractors. Compile progress reports (networks, bar charts & “S” curves) for weekly management meetings. Produce a three-week look-a-head schedule for construction based on priority availability.

COMPANY:        L & C STEINMÜLLER CONSTRUCTION                 DUR:                DEC 94 TO JAN 96

POSITION:        HYDRO / PRESSURE TEST CO-ORDINATOR *       CLIENT:            SASOL

PROJECT:          ACN RELOCATION PROJECT SASOL III SECUNDA

Allocating isometric drawings to systems for pressure testing. Provide all logistical support for pressure testing. Inspection prior, during and after testing. Gather all relevant documentation and certificates. Compile test packs and final handover documentation.

NOTE  * : The two positions above were run concurrently.

COMPANY:        L & C STEINMÜLLER CONSTRUCTION                 DUR:                3 WEEK SHUT DOWN

POSITION:        JUNIOR PLANNING ENGINEER                            CLIENT:            SASOL

PROJECT:          OXYGEN PLANT SHUT DOWN SASOL III SECUNDA

Devise shut down schedules and monitor progress accordingly. Provide information required by senior planner for management reports, presentations and meetings.

COMPANY:        BABCOCK CONSTRUCTION                                 DUR:                OCT 94 TO NOV 94

POSITION:        DOC CONTROLLER / QA CO-ORDINATOR            CLIENT:            SASOL

PROJECT:          ACN RELOCATION PROJECT SASO III SECUNDA

Assemble ‘As Build’ drawings. Implement and maintain a pressure test schedule. Construct QA/QC data packs and final handover documentation. Document control function to maintain ISO 9000 standards.

COMPANY:        BABCOCK CONSTRUCTION                                 DUR:                AUG 94 TO OCT 94

POSITION:        SPEC. WELDING CO-ORDINATOR / INSPECTOR   CLIENT:            SASOL

PROJECT:          ACN RELOCATION PROJECT SASOL III SECUNDA

Perform NDE testing on newly erected vessels and tanks as per client specifications. Welding tests on piping and support steel work. Generate the required documentation and specifications for repairs to operating pipelines.

 COMPANY:        BABCOCK CONSTRUCTION                                 DUR:                JULY 94 TO AUG 94

POSITION:        SPECIALISED LOGISTICS TECHNICIAN                CLIENT:            SASOL

PROJECT:          ACN RELOCATION PROJECT SASOL III SECUNDA

Complying with ISO 9000 standards. Applying QCP specifications to pressure vessels and tanks that were for rebuild or refurbishment. Acquiring all materials, transport and labour to ensure speedy repairs and installations.