Project Scheduler, FMC Technologies, Gumusut Kakap Subsea
START Date:
June, 2008
END Date:
May, 2010 1. Maintained and updated engineering and production schedule of Subsea Manifold and Tie in System
2. Monitored progress of subsea valves manufacturing at Johor plant
3. Monitored progress of procurement for Riser
Experience Hours (Planning & Scheduling):
4000 - Company:
- Industry:
- Job Role:
- Project:
- Region: