Construction / Fabrication Planner , ITA for TECHNIP France (BP Subsea Project), Subsea installation in Angola

START Date: 
January, 2009
END Date: 
April, 2010

ITA – Mission with TECHNIP (Sub sea Branch) for BP

« Planning support for a project of sub sea installation in Angola »         

Tasks:       

Construction / Fabrication planner:

  • Realization of level 4 fabrication schedules for Angolan base (piping and structures) and coordination with other projects realized in parallel.
  • Construction Manhours / Mobilization estimate.
  • Feasibility review looking on storage and lifting equipment.
  • Setting up of the construction progress measurement system
  • Clarification with Angolan yards for sub-contracted activities and follow-up
  • Support to subcontractors and suppliers for setting up of acceleration plan and follow-up

Support to Engineering planning leader:

  • Preparation of tools for the following of reception of comments from Company for critical eng. Documents.
  • Estimation of schedule impact of variation orders.
  • Review, comments and following of suppliers schedules.
  • Preparation of following tools dedicated to transport activities and interfaces between suppliers.