Planning Engineer, Daewoo E&C, EGTL (Escravos Gas to Liquid Project)

START Date: 
May, 2010
END Date: 
February, 2011
  • Main scope includes Engineering, Procurement and Construction work (Temporary facilities, Civil, Architecture, UG/AG Piping, Mechanical, Electrical, Instrument, Insulation, Painting & Pre-Commissioning).
  • Developing of EPC Master Schedule using Primavera P6 Software , up to Level 5 as per contract requirement
  • Involved in preparation of Progress Measurement of Engineering, Procurement and Construction work, along with invoice submission.
  • Weekly/Monthly/Daily reports generation including ā€˜Sā€™-curves for client & management review.
  • Resource planning cost control, Progress Monitoring and progress analysis along with Internal and external reporting.
  • Provide progress reports, graphs and critical path analysis for the monthly and weekly progress reports to the PMC.
  • Analyzing progress shortfall on Daily, Weekly and Monthly basis, attending Weekly Review Meeting with updated Minutes of Meeting (MOM) discussion minutes, Updating and Modification of schedule as per requirement.
  • Creating Purchase Requisition  by using SAP software
  • Monitoring and controlling the Engineering Documents for Weekly and Monthly progress.
  • Preparation of 3 weeks Look ahead schedule and distribute to all discipline Managers and Supervisors.
  • Closely follow up with procurement team for weekly reports updating and get the ETA date for important materials.