Construction & Commissioning Planner, Jacobs Catalytic, Commissioning Scheduling & Logistics Coordinator Projects
START Date:
September, 2001
END Date:
August, 2003 Logistics Coordinator
- Multi-tasking of various assignments and projects that included interfacing with ACJV, Shell and Jacobs Catalytic Supervisors, Foreman, Craft Leads and Management personnel.
- Coordinated and planned the overall requirements to supply Commissioning and Maintenance Organization with support facilities and services: Temporary trailers, telephones, radios, office equipment, scaffolding lay-down, rental equipment, tools, consumable storage areas, issue facilities, material marshalling areas, parking and traffic flow logistics at Shell Scotford's Upgrader Facility.
- Scheduled and coordinate permit requirements for contractor personnel to complete equipment service maintenance as planned.
Commissioning Planner/Project Controls Specialist
- Managed the overall schedule for commissioning, pre-turnaround, turnaround and post turnaround activities.
- Reported to the Refinery Management Team and Commissioning Steering committee on tracking progress of work, costs, schedule delays and completions.
Experience Hours (Planning & Scheduling):
2000
Experience Hours (Cost Management):
500 - Company:
- Industry:
- Job Role:
- Project:
- Region: