Senior Planner, Costain, Alba Potline aluminium smelter and associated works

START Date: 
September, 1990
END Date: 
December, 1991

 

1990 – 1991:  Costain, UK: Senior Planner

Bahrain, Gulf

Project planning, monitoring and reporting (including earned value productivity based upon manhour expenditure) of Alba Potline aluminium smelter and associated works (process facilities, sub-station, deep pits at sea level). Contract management/planning, client liaison and co-ordination of associated aluminium process facilities completed major works ahead of schedule. Based in Manama throughout the period of the Gulf War. Experience working for major contractor to Bechtel.