4D Planning Consultant update base line schedule review, BIM Evolution, Curtin University - Midland Health Campus - 4D Planning

START Date: 
January, 2018
END Date: 
March, 2018

Engaged as 4D Planning consultant to create a 4D Model form the tender schedule. The use of 4D extended to validating schedule logic as part of the schedule review process to establish an agreed construction programme. The project included Hazard Identification workshops and schedule re-sequencing for optimisation.

 

https://www.youtube.com/watch?v=MccU75-IgZM

Experience Hours (Planning & Scheduling): 
250