Senior Planning Manager / Complex Build Integrator, MACE GROUP LIMITED, T1 Baggage Replacement Heathrow Airport

START Date: 
January, 2010
END Date: 
April, 2011

     

This was an upgrade to the existing Baggage Systems where Mace where the Principle Contractor for the works. It involved creating an integrated schedule that allowed multiple contracts to be sequenced and coordinated in a live operating environment and confined working spaces. Associated works required civil loading calculations to be undertaken to support the new increased and extensive structure loadings. Numerous footings required breakout and recasting to meet new design specifications. Associated temporary load bearing points needed to be designed to accommodate these additional civil works. Buried service scans where undertaken due to deeper and enlarged footprints. The entire Upgrade comprised of Structural re-enforcement, Baggage Design & Installation, M&E installations, Civil’s ground foundation improvements and commissioning prior to the Olympics 2012 Embargo.

  • Set processes in place to manage Complex Build Integrator role on behalf of Mace
  • Managed Planning resource for the integration of schedules & Implemented Project Control procedures & Reports as required by Project Controls Manager.
  • Managed the Data quality, and compiled weekly overview status reports to client and management teams.
  • Reviewed critical path activities with all contractors in order to provide Project Managers with possible solutions/mitigation strategy that may have been required.
  • Managed Mace site planner and cross-checked the Mace site schedule for quality and accuracy of data.
  • Cost Loaded & Produced CPI / SPI reports for period end reporting.
  • Analysed and discussed integrated programme issues weekly with project planning teams to address integration issues.
  • Evaluate, Analyse, and implement programme compensation events on behalf of Mace in line with NEC3 contract clause parameters.
  • Managed our Baseline & database administration.
  • Monitor and track KPI & Contract dates.
  • Cover planning role requirements when planning resources are on holiday
  • Hands On regular site visits with planners & management site teams.
Experience Hours (Planning & Scheduling): 
2100
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
150