Senior Planning and Cost Control Engineer, United Arab Emirates, Abu Dhabi, EPC Project for Rihan Heights District Cooling Plant – Mubadala Properties, UAE.
Dec, 2009 – Present, Senior Planning and Cost Control Engineer, Kharafi National Co.
EPC Project for Rihan Heights District Cooling Plant – Mubadala Properties, Abu Dhabi, UAE.
Rihan Heights District Cooling Plant will serve Al Sowwah Island which will include office buildings-stock exchange-retail-parking-five star hotel-six star resort hotel and world class hospital (Cleveland Clinic Abu Dhabi).
During this current project assignment my responsibilities include:-
- Preparation of the detailed Baseline Schedule in conjunction with the Project, Construction, Engineering and Procurement Managers.
-Collecting the necessary information to prepare the detailed Bill of Prices.
-Preparing the Cost Breakdown Structure.
-Preparing the Earned Value data sheet, loading the data into the Project Program and using it for Earned Value monitoring of project progress.
-Preparing the Manpower Histogram and Quantity Curves.
-Preparing the Cost Loading Construction Schedule.
-Preparing Cash Flow Histograms, S-Curves and forecasting for monthly invoices.
-Preparing the Progress S-Curves for Overall Project, Design, Engineering, Procurement, Construction and Commissioning.
-Preparing the Design, Procurement and Shop Drawings Logs which are extracted from Baseline Schedule and then report the ‘’follow-on’’ actions in the Logs for Design, Procurement and Engineering Departments.
-Preparing the Schedule Model (Schedule Method Statement) which shows how the flow and sequencing of the activities are progressing towards completion of the Project.
-Monitoring Cash Flow analysis on monthly basis.
-Regularly reviewing (weekly/monthly) critical and sub-critical activities and monitoring their impact on the project schedule.
-Participating in the progress meetings and any other meeting related to revision of the Project Program.
-Preparing weekly Look-Ahead Programs from the Master Schedule and monitoring the same.
-Updating the Construction Schedule and the Cash Flow.
-Prepare the monthly and weekly progress reports and identifying the causes of delay if any and the effect of delay on the Construction Schedule.
-Preparing Acceleration Plans.
-Reviewing and evaluating all requests for time extension.
-Preparing the Project Forecast Report ( Cost Report).