Planning Engineer, Consolidated Contractors International Company (CCC) of Greece, General Utilities Plant Expansion Project, Ruwais, Abu Dhabi, United Arab Emirates
PLANNING ENGINEER for Consolidated Contractors Int’l Company [CCC] of Abu Dhabi, UAE
Project & Place : General Utilities Plant Expansion Project, Ruwais, Abu Dhabi, United Arab Emirates
Consultant and Client : Chiyoda Corporation, Japan and Abu Dhabi National Oil Company (ADNOC)
Value : UAE Dirhams One Hundred (100) Million i.e. US Dollars 27 Million
Scope of Work of the project:
Construction of Piping & Equipment foundations, Discharge Culvert, Combined Utility & Auxiliary Switchgear Buildings. Fabrication & erection of structural steel pipe racks, bridges & supports. Fabrication, erection & testing of CS, SS, GI, Cu-Nickel clad/solid, GRE (Glass Reinforced Epoxy), RTRP (Resin Threaded Reinforced Plastic) & PTFE lined piping. Erection & installation of Gas Turbine Generator, Waste Heat Recovery Boiler, Multi Stage Flushing Desalination unit and other equipment & vessels. Tank modification works i.e. structural steel roof supports, internal piping, valves & nozzles. Piping tie-in works (168 nos.) requiring shutdown or hot tapping. Installation of transformers, switchgears, cathodic protection and instrumentation works. Refurbishment of existing control room. Commissioning.
Duties & Responsibilities
1) Planning, Scheduling & Control by preparing & updating Construction Schedules, Three Weeks Look Ahead Schedules, Tie-ins & Shutdown Schedules and Hot Tapping Schedules in the form of CPM Network & Bar Chart using Primavera Project Planner (for DOS), Microsoft Excel & Word. Attending Weekly Meetings.
2) Estimation & allocation of resources. Development of Progress Measurement System. Progress monitoring
& reporting through Daily, Weekly & Monthly Reports including Progress Assessment Curves.