Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Scheduler, Hatch Energy, Surmont Phase II

START Date: 
April, 2006
END Date: 
December, 2006
  • Developed construction and pre-commissioning activities based on a detailed quantity take-offand contractor schedule inputs.
  • Provided pre-commissioning, commissioning and start-up planning support.
  • Coordinated with Operations, Engineering and Construction to identify project scheduledeviations and possible corrective actions.
  • Supported the preparation of month end reports, projections and curves as required by theControls Management Team.
  • Effectively and accurately communicated relevant project information, including resources,progress, forecast to go and schedules to project team members and management.
  • Assisted in the preparation of impromptu reports for client use.
  • Supported the preparation of shift reports, man-power curves, cost estimates and site-wideconstruction progress and milestone charts for all contractors.
  • Encouraged an atmosphere of participation in continuous improvement and scheduleeffectiveness.
  • Assisted contractors with schedule development and ensured that contractor schedules were inlinewith master project schedule by cross-checking project milestones.
  • Liaised with onsite contractor schedulers to ensure consistency and correctness of informationreported.
  • Trained contractors in Two-week look-ahead development and maintenance.
  • Effectively optimized the most critical sub-project on the jobsite; the main wellpad constructionSchedule.