SENIOR PLANNER, Adyard Abu Dhabi, Multiple Refinery Capital and Maintenence Projects
START Date:
January, 2009 Ø Identification of job volume, criticalness, material requirements, rigging requirement & Pre-T/A arrangement through site visit and scope studies.
Ø Developing the activities, logic & resources for the assigned project sub-elements leading to the creation of the baseline schedule
Ø Creating and assigning specific activity codes for activities.
Ø Creating and assigning specific calendars for activities
Ø Identifying areas of uncertainty and applying appropriate allowances
Ø Development of Base Line Schedule using Planning Software PRIMAVERA (P6).
Ø Set work program and target milestones for each phase based on the project plan.
Ø Interact with project team and task managers to define scope of work to develop and update detailed schedules,
Ø Identification of sub-contractor jobs and submitting request
Ø Preparation of workbook with all necessary documents and getting approval from client
Ø Preparation of method statement for critical jobs and Attending Task Risk Assessment meeting for critical jobs.
Ø Identification of plant and machinery requirements.
Ø Identification tools and consumable requirements.
Ø Identification critical lifting locations and preparing rigging study with rigging specialist
Ø Extracting total man-hours from baseline schedule thereby extracting manpower requirement on each day of turnaround.
Ø Identification of supervisor and foreman requirement based on job locations and volume.
Ø Preparing manpower histogram and extracting resource from it
Ø Distributing manpower to various area of Turnaround in accordance with the approved man hours.
Ø Preparing equipment plot plan.
Ø Preparing job tracking sheet and job control sheet.
Ø Assist project team to develop and maintain periodic status reports to keep management informed on project progress.
Ø Collecting and updating daily progress and creating report with job forecast, highlights and S-Curve.
Ø Creating look ahead plans.
Ø Tracking the criticality of the main paths to completion and float consumption
Ø Assessing and incorporating the impact of approved changes and any deviations from the key project targets and milestones, including productivity monitoring and identification of alternate approaches to optimize the plan.
Ø Creating recovery and back up plans.
Ø Contributing to close-out data to enable knowledge retention (lessons learned, project data compilation) at completion of work.
Experience Hours (Planning & Scheduling):
40000
Experience Hours (Cost Management):
8800 - Company: