Assistant Program Manager, ADtranz Transportation S/B , STAR LRT (Light Rail Transit) Phase II
START Date:
March, 1998
END Date:
March, 1999 - Planning and scheduling for E&M works for Power Supply, Telecommunication, Automatic Fare Collection, SCADA and Rolling Stock for STAR LRT Phase II
- Liaison with civil partner for the integration of E&M schedule
- Produce three-weekly programme, E&M Works Programme, Target programme and Monthly Progress Report
- Manage and develop the Project Progress Reports not limited to Monthly Progress Report, 3 Month Rolling Programme, Key Issues Report, Subcontractor Document Submission Schedule
- Generate monthly progress payment claims for work completed
- Design and development of software application in Microsoft Access to track the Site Test Report information after Site Inspection
- Development of a Defect Management System (DMS) for use by the Client (STAR) using MS Access
in order to monitor any trains which register defects during operations