Assistant Quantity Surveyor, Obayashi Corporation, Saigon East-West Highway Construction Project Construction of Tunnel Crossing Saigon River and Construction of New Thu Thiem Road
START Date:
September, 2009
END Date:
May, 2015 Quantity Surveyor
Taking off quantity
Assisting in building detail unit price analyzing
Making and analyzing Cost estimate of price adjustment.
Managing price indices data and other necessary sources to apply in fluctuation calculation
Providing adjustment data to build up Interim Monthly Statement
Assisting Chief Quantity Surveyor to prepare financial reports, Statements, monthly claims.
Assisting in calculation Project’s budget at each phase
Experience Hours (Planning & Scheduling):
7000
Experience Hours (Cost Management):
6000