Project Scheduler, WorleyParsons, 880 MW Gas Turbine Combined Cycle Plant
START Date:
August, 2009
END Date:
April, 2010
EPCM schedule for 880 MW Gas Turbine Combined Cycle Plant on the premises of the existing Varna Thermal Power Plant.