Project Planner

Project Planner, Cahaya Jauhar Sdn Bhd, Johor UMNO Office Complex, Malaysia

START Date: 
December, 2013
END Date: 
December, 2014
Role & Duties:
  • Scheduling for Pre-Development Stage i.e Design Management, Cost Management, Authority Approval, and Procurement Management
  • Review and analysis schedule and resource plan submitted by contractor
  • Review and analysis progress report and chronology of events submitted by contractor
  • Prepare progress report to the Executive Commitee and Client
  • Review, analysis and recommend Extension of Time submitted by contractor
Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
400

Project Planner, Bina Schedulers Sdn Bhd, Fourth Lane Widening for North South Expressway, Malaysia

START Date: 
June, 2013
END Date: 
December, 2013
  • Project Planning and Scheduling for Linear Project with PRIMAVERA P6 R8.2.
  • Project Progress Reporting with Oracle Enterprise Performance Management System.
  • Delay analysis for Extension of Time application.
Experience Hours (Planning & Scheduling): 
950

Project Planner, Bina Schedulers Sdn Bhd, Foundation works for Damansara Uptown Mixed Development

START Date: 
September, 2012
END Date: 
February, 2013
  • Project Planning and Scheduling for Mixed Development Project.
  • Project Progress Reporting.
  • Delay analysis for Extension of Time application.
Experience Hours (Planning & Scheduling): 
550

Project Planner, Bina Schedulers Sdn Bhd, Foundation Works for Icon City Mixed Development, Petaling Jaya, Malaysia

START Date: 
September, 2012
END Date: 
February, 2013
  • Project Planning and Scheduling for Mixed Development Project.
  • Project Progress Reporting.
  • Delay analysis for Extension of Time application.
Experience Hours (Planning & Scheduling): 
550

Project Planner, N G Bailey & Co, Georges Dock Building, Liverpool

START Date: 
March, 2014

Georges Dock Building, Liverpool UK

The Georges Dock Building based in Liverpool UK was refurbishment project, converting unused office/storage space into a brand new, state of the art combined control room for Mersey Travel (Client) & Merseyside Police for the overseeing of the Mersey Tunnels.

The main use of the building itself is to supply fresh air, and extract fumes from the tunnels it is linked to however, it was the offices contained within the actual building that were being transformed. 

My ro

Experience Hours (Planning & Scheduling): 
350

Project planner, Cimolai, Maintenance Hangar Doha Airport, Warsaw National Stadium

START Date: 
July, 2005

I worked as a planner in several international project in the last 8 years for a big structural steel fabrication and erection Italian company.

I've been working trought several project in Qatar, Poland, Italy, Panama working with Primavera P.3 and P.6 for scheduling and reports.

Project Planner, National Air Traffic Services (NATS), Software and Hardware Upgrade Projects

START Date: 
February, 2002
END Date: 
February, 2004

2002-2003                            NATS Military Systems - Department Project Planning – Project Planner

 

Joined the Military Systems, Software Development Division to assist in the development of Project Planning and to develop the Project Standards.  Responsible for planning SLAs Interfacing with Middle Management and all staff within the Division.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1000

Project Planner, National Air Traffic Services (NATS), All Software Projects

START Date: 
February, 2000
END Date: 
January, 2002

2000-2002            NATS Software Services - Department Project Planning – Project Planner

Trained in all aspects of project planning to introduce project standards into the Software Development Division.  Included Leading on the management of the Training and Development Systems for the department.  Achieved capturing true project costs through the introduction of a new timesheet administration system for circa 40 staff.

Interfacing with the senior Management team and all staff in the Division.

Experience Hours (Planning & Scheduling): 
3000
Experience Hours (Cost Management): 
1000

Project Planner, InnoLead Consulting, Mining Plant Expansion

START Date: 
September, 2006

.  As Project Planner in various projects my responsibilities are to:

·         Conduct project activity planning

·         Scheduling of activities (with input from contractors) and project controller into an integrated critical path schedule

·         Development of project WBS and work plan

·         Prepare and maintain resource loaded schedules and maintain S-curves.

Experience Hours (Planning & Scheduling): 
16000

Project Planner, INNOLEAD CONSULTING, Mining Plant Expansion

START Date: 
April, 2014

.  As Project Planner in various projects my responsibilities are to:

·         Conduct project activity planning

·         Scheduling of activities (with input from contractors) and project controller into an integrated critical path schedule

·         Development of project WBS and work plan

·         Prepare and maintain resource loaded schedules and maintain S-curves.

Experience Hours (Planning & Scheduling): 
16000