Smith Started with a 2day P6 course, then went into planning for a Building Envelope company using Asta Power Project, were I developed my skills on sequencing, updating and delay analysis programming.
Current working with P6 for a large Infrastructure company on a Nuclear site. Design/work comes through via instructions from the client, this then goes into the program and scheduled with resource and cost.
the program then has delays, due to the late design and resequncing of works.
The unfortunate side of this, is that there are no fixed design milestones, so we are unable to set a true agreed baseline, which makes the NEC3 contract difficult.