Hatem Elkarnashawy
Hatem Abd Alla El Karnshawy
Projects ManagerBSc, PMP, C.Eng, CP, M.ASCE
Contact Information: ………………………. Current Address: Kuwait Tel: 0965- 97879753 (Kuwait) + 20103104100 (Egypt) E-mail: Hatem.Abdalla@windowslive.com Website: www.Eng-Hatem.net |
Summary: |
Well qualified Civil and Construction Engineer with extensive experience in Project Management, worked in various construction projects. Following safety procedures .Extensive knowledge and skills in Contract Procurement, Contract Management, Contract Administration, Claim Analysis, Dispute Resolution, Pre-contract Documentation, Contractual Arrangement, Project Cost Control and Cost Plan, Price Analysis etc. gained in a wide range of Public and Private Sector with Multi-disciplinary Contract environment. , Delays Analysis, Payments and reporting to client.
Education: |
Ø Graduation: Bachelor of Civil Engineering, June 2002 Alexandria University, Egypt – Faculty of Engineering
Ø Graduation Project: Waste Water Treatment - Grade: Excellent, (Awarded the Magia Prize)
Ø Certified Project Management Professional – PMP - from Project Management Institute – USA
Ø Preliminary Certificate (Principles of law and contract theory, Commercial Law, Law of Civil and Commercial Procedure) , Arbitration Diploma from Cairo University, Egypt – Faculty of Law
IT and Computer Capabilities: |
Ø Planning/Scheduling: Primavera Project Planner 6
(Project Management Client Server– Advanced Project and Resource Management)
Primavera Project Planner 3.1 (48 Hrs), SureTrak Project Manager 3 , MS Project, Claim Digger
Ø Contract Manager:Expedition Contract Manager
Ø Microsoft Office Specialist (MOS) Level Expert
Ø International Computer Driving License (ICDL)
Ø Engineering: AutoCAD Structure Design: SAP 2000
Syndicate & Societies : |
ØFull Member M.ASCE of American Society of Civil Engineers Membership ID No. 441499
ØProject Management Institute, PMI- USA, Membership PMI ID No. 1217305
ØFull Member of Kuwait Society of Engineers – Kuwait, Membership ID No. 17763
ØFull Member of Engineers Syndicate, Alexandria –Egypt, Membership ID No. 25/2290
ØMember of Federation of Arab Engineers
Safety and Health: |
Ø CERTIFIED BY American Heart Association First Aid & CPR, AED –
Accredit BY Occupational Safety and Health Administration (OSHA)-USA.
Ø CERTIFIED BY Occupational Safety and Health administration (OSHA) -USA Construction– 30 Hr.
Ø CERTIFIED BY Hyundai Heavy Industrial- Explosive Ordinance Disposal Awareness Session (EOD) and Health, SAFETY and Environment Induction (HSEI) - Oil Field Safety
Language Ability: |
Ø Arabic (Mother Tongue)
Ø English Fluent (Reading, Writing, Speaking), TOFEL course at Kuwait University
Personal Information: |
Nationality: Egyptian
Work experience: |
State of Kuwait:
NAKHEEL UNITED REAL ESTATE COMPANY, FROM 24 January 2010 UP TO Date
PROFESSIONAL: | Projects Manager |
Design Projects |
|
|
|
| Kuwait Finance Bank - Local Real Estate Department – Kuwait
|
PROJECT TITLE | · Residential complexes Residential complex in Dasman project - 15,000 m2 Offices complex in Al Watya project – 20,000 m2 Residential complex in Jabriya 8,000 m2 Residential complex in Jabriya – 4,000 m2 Residential complex in Mahboula – 4,000 m2
· Commercial complexes Commercial complex in Dejeej – 5,000 m2 Commercial complex in Jleeb al Shukh – 4,000 m2
· Residential buildings Residential building in Bneed al kar – 1,000 m2 (9) Residential buildings in various area in Kuwait (6) Residential buildings in various area in Kuwait
· Villas (11) Private Residential villa in Funatees
· Others Permits for 21 building in various area in Kuwait
|
| Nakheel United Real Estate Company
|
PROJECT TITLE | · Towers Nakheel tower – Bahrain · Resorts Al Khiran Resort – 21 villa · Residential buildings Aknan residential building – Salmiya
|
RESPONSIBILITIES | 1. Prepare contracts between Nakeel united and Kuwait financial bank for design and permits phase. 2. Following up the process of design and permits phase till singing contact with the owner contractor. 3. Review all the drawing and documents submitted by consultants. 4. Value engineering and cost saving for the projects. 5. Prepare terms of references TOR for the projects. 6. Prepare list of recommended consultant’s offices. 7. Collect the financial and technical offers form consultant’s offices and open it with client. 8. Follow up, study and submit recommendation to the client of all submissions from the consultant. 9. Study time extensions submitted by consultant and issue recommendations to client. 10. Study Payments submitted by consultant and issue recommendations to client. 11. Prepare Nakeel united company payments for my projects. 12. Prepare projects closeout payments and documentations. |
Execution Projects |
|
CLIENT | Nakheel United Real Estate Company |
PROJECT TITLE | AL KHIRAN RESORT |
SCOPE OF WORK: | Construction, Completion and Maintenance of21 No. Furnished Villa And Landscape, Swimming Pools… |
CONTRACT VALUE | 800,000 KD , 3,200,000 $ ( Cost Plus contract) |
RESPONSIBILITIES | 1-Review for approvals the contracts between Main contractor and subcontractor. 2-Follow up the progress at site. 3-Review for approvals the submitted payments and CPM program. 4-Meet supplies, obtain quotations, study the submissions and submit a recommendation to higher managements at the company. 5- Review for approvals the any quotations submitted by contactor m study the recommendation and finalize the subject. 6-Follow up the progress at site and direct the contractor to avoid delays and keep high level of safety. 7-Finalize architecture, swimming pools, drawing obtain approvals from higher management.
|
STANLEY (USA), JASSIM QABAZARD (Kuwait) AND AIRWAYS (new Zealand)(JOINT VENTURE) CONSULTANTS
FROM 2 MARCH 2008 TO 04 November 2009
CLIENT | Directorate General Of Civil Aviation –Planning & Control Department |
PROJECT TITLE | KUWAIT AIRSPACE SYSTEM PLAN (KASP) including subproject as: 1- Kuwaitcontrol & metrological center 2- Electrical Infrastructure &South Power Building Project 3- Communication System Project 4- Air Traffic Management System Project 5- Surface Movement Radar Project 6- Airport Surveillance Radar Project 7- Instrument Landing System Project 8- KuwaitAirportData Interchange Network |
SCOPE OF WORK: | Consultancy For The Project Management And Supervision Of Works Involved In The Implementation Of The Kuwait Airspace System Plan At Kuwait International Airport |
POSITION: | Senior Planning Engineer / Cost Control |
CONTRACT VALUE | 234,300,283 KD , 937,200,000 $ |
RESPONSIBILITIES | Creating, following up &updating KASP overall program & overall monthly report, tentative schedule for projects under tendering. Detecting delays in each subproject and to the overall, Review each subproject CPM program, analyses critical path for each subproject after/before updates, Cost loading, Resource loading, Method of Statement, Payments, Variations, Monthly Reports submitted by contractor. Monitor the progress at site. Attending & participate at progress meetings. Review and validate extension of time claims submitted by contractors. Analysis all delays in the KASP project and Subprojects.
|
TOTAL MANAGEMENT CONSULTANCY PROJECT MANAGEMENT & FEASIBILITY STUDIES
FROM 2 JULY 2007 UP TO 30 DECEMBER 2007 – Position Planning Engineer
PROJECT TITLE : | CRYSTALTOWER |
SCOPE OF WORK: | Construction, Completion and Maintenance of the CRYSTAL Tower -50flr + Podium +Parking |
CONTRACT VALUE | 17,400,000 KD , 70,000,000 $ |
PROJECT TITLE : | HOLYDAY INN HOTEL |
SCOPE OF WORK: | Renovation of the three Hotel towers – 4 Towers |
CONTRACT VALUE | 2,500,000. KD , 10,000,000 $ |
PROJECT TITLE : | WARBAHEAD QUARTER TOWER |
SCOPE OF WORK: | Construction, Completion and Maintenance of the WARBA TOWER-24flr + Podium +Parking |
CONTRACT VALUE | 2,199,947.892 KD , 8,800,000 $ |
PROJECT TITLE : | THE NEW CENTRAL VEGETABLE & FRUIT MARKET IN SULAIBIYA -BID PACKAGE - MEP WORKS |
SCOPE OF WORK: | Elect Mechanical Works |
CONTRACT VALUE | 8,441,551 KD , 34,000,000 $ |
PROJECT TITLE : | RESIDESIAL COMPLEX – FARAWANIA |
SCOPE OF WORK: | Construction and Completion |
CONTRACT VALUE | 1,718,376.5 KD , 6,500,000 $ |
RESPONSIBILITIES | Creating, following up &updating CPM program, Cost loading, Resource loading, Method of Statement, prepare & submit monthly reports, Attending & participate at progress meetings. Monitor the progress at site. |
BADER AL MULLA & BROS. CO.
FROM 25 DECEMBER 2006 UP TO 2 JULY 2007 Position Planning & Cost Control Engineer
PROJECT NAME: | THE NEW CENTRAL VEGETABLE & FRUIT MARKET IN SULAIBIYA -BID PACKAGE - MEP WORKS |
SCOPE OF WORK: | Elect Mechanical Works |
CONTRACT VALUE | 8,441,551 KD , 34,000,000 $ |
PROJECT TITLE : | KUWAITREGENCY HOTEL PALACE RE-DEVELOPMENT |
SCOPE OF WORK: | Elect Mechanical Works |
CONTRACT VALUE | 2,900,979.913 KD , 12,000,000 $ |
|
|
RESPONSIBILITIES | Creating, following up &updating CPM program, Cost loading, Resource loading, Prepare & submit monthly reports, Attending & participate at progress meetings. Monitor the progress at site.Prepare & submit monthly payments, variations.
|
MUSHRIF COMPANY FOR TRADING & CONSTRUCTION
FROM 15 MAY 2004 UP TO 08 OCTOBER 2006 Planning Engineer- Site Engineer
PROJECT TITLE : | EXPORT CRUDE OIL FACILITIES-TANK NTF- KOC - HYUNDAI HEAVY INDUSTRIAL |
SCOPE OF WORK: | Foundations for crude Oil tanks –Earth Work |
CONTRACT VALUE | 5,250,000 KD , 21,000,000 $ |
PROJECT TITLE : | ZAKAT HOUSE HEADQUARTER PROJECT IN SOUTH SOURA |
SCOPE OF WORK: | ZAKAT HOUSE HEADQUARTER-BUILDING |
CONTRACT VALUE | 4,198,000 KD , 17,000,000 $ |
RESPONSIBILITIES | Creating, following up &updating CPM program, Prepare & submit monthly reports, Attending & participate at progress meetings. Monitor the progress at site. Prepare & updating all types of logs, submittals and daily reports. |
PROJECT TITLE: | AHMADY PROJECT – RA/34 |
SCOPE OF WORK: | ROADS {HIGHWAYS-RAMPS}-PRE-CAST YARD {GALLEYS- MANHOLES} |
PROFESSIONAL: | Site Engineer |
CONTRACT VALUE | 6,000,000 KD , 24,000,000 $ |
PROJECT TITLE : | NORTH DOHAPROJECT - RA/97 |
SCOPE OF WORK: | BOX CULVERTS –COFFER DAM- DEWATERING |
CONTRACT VALUE | 4,250,000 KD , 17,000,000 $ |
RESPONSIBILITIES | Prepare & submit daily reports, responsible for casting concrete at Pre-Cast yard, calculating required steel and concrete. Assistant in prepare materials submittals, prepare & submit daily reports , responsible for casting concrete, calculate productivities to maintain the CPM dates, calculating required steel and concrete. Maintain & updating ISO requirement at site.
|
Egypt:
Ø Alexandria Petroleum Company
Ø Mamdoh Hamza office-San Stefano Hotel Project
Ø RAYD Company for Construction in Arab Academyfor Science & Technology & Maritime Transport site (Building)
- Industry:
- Region: