kesa khanthapraisi
Professional Experience :-
December 2007-April 2009 : Tipakorn Co.,Ltd
(Design and Contractor Company)
Position : Senior Civil Engineer
Project : Connection Bang-Plee Susawat Industrial Ring Road
Interchange Road , Elevated Road, Toll Building and Toll Plaza The construction cost is 2,472 Million Baht.
Job Description : -Preparation Construction Schedule and monitoring work.
-Breakdown Direct Cost for Control Budget and Sub-Contractor.
-Preparation Survey Data for Construction.
-Preparation Shop Drawing for Construction.
-Break Down Quantities for Order Material at Site (QS).
-Preparation Main Payment and Sub-Payment.
-Designing Temporary Support and Formwork for Structure Work.
-Document Control .
December 2007-April 2009 : For-Con Engineering Co.,Ltd
(Design and Contractor Company)
Position : Project Engineer
Project : Office Building of National Intelligence Agency
The Office Building is in Cha-am, Pretchaburi and Ang Sila, Chonburi that spreads 3 levels are reception room, meeting hall and facilities hall . For in Ang-Sila Project there are another three buildings as follow: 20 rooms of apartment, food court and reception residence for VIP. The construction cost is 40 million Baht
Job Description : -Preparation Construction Schedule and monitoring work.
-Breakdown Direct Cost for Control Budget and Sub-Contractor.
-Break Down Quantities for Order Material at Site (QS).
-Preparation Main Payment and Sub-Payment.
-Designing Temporary Support and Formwork for Structure Work.
-Document Control .
.
August 2004-December 2007 : TC Joint Venture (Contractor Company)
Position : Project Engineer
Project : Southern BangkokOuter Ring Road (SOBRR)
Section 3 (Bridge Approach)and Section 4 (Sukhumvit Road)
An approximate 3,945 m. of Elevation Road with 3 lanes traffic in each direction. This project include dia. 0.80 m. spun pile and dia.1.20 m. bored pile, The Post-tension of Segmental Box Girder(D4), The pre-stress of Girder span length 30 m., Hollow Column (40-8 m. Height), RC. Deck Slab with asphaltic concrete and also applied to construction project. The construction cost is 2,700 Million Baht.
Job Description : -Preparation Construction Schedule and monitoring work.
-Breakdown Direct Cost for Control Budget and Sub-Contractor.
-Preparation Survey Data for Construction.
-Preparation Shop Drawing for Construction.
-Break Down Quantities for Order Material at Site (QS).
-Preparation Main Payment and Sub-Payment.
-Designing Temporary Support and Formwork for Structure Work.
-Document Control .
March 2003-July 2004 : Team Consulting Engineering and Management Co.,Ltd.
(Consulting Company)
Position : Civil Engineer
Project : New Bangkok International Airport (NBIA)
1. Water Supply and Wastewater Collection System
The Work Consist of the construction of piping infrastructure and related facilities to distribution potable water to the airport’s facilities
2. Power Distribution and Duct bank Network Systems
3. Airport Maintenance Facilities
The construction cost is 1,900 Million Baht.
Owner : New Bangkok Internation Airport Co.,Ltd.
Job Description : Responsible for review and make commendation to NBIA on the acceptability of construction schedule, Monitor the
contractor’s progress, review and verify the contractor’s
daily recourse report, prepare the monthly progress
reports, produce percentage completion curve, budget
status of the contract updated on monthly basic.
March 2002-Febuary 2003 : Shimizu Corporation (Contractor Company)
Position : Civil Engineer
Job Description : Break down the cost for tendering. Prepare the
prequalification document for the Airfield Pavement,
Elevated Road, Landside Road of NBIA ,any plant project.
February 1999-February 2002: Epsilon Co.,Ltd. (Consulting Company)
Project : Sri-Ayutthaya - Asoke Dindaeng Elevated Road.
An approximately 2,350 m. of Elevation Road with 2 lanes traffic in each direction.This project include dia. 0.60,0.80,1.00 m. -bored pile, Both wet and dry process; dia. 0.30,0.60 m. -spun pile ,The pre-stress concrete of Girder, Rc deck and slab with asphaltic concrete and also applied to the construction project. The construction cost is 775 Million Baht.
Owner : BangkokMetropolitan Administration
Position : Site Engineer
Job Description : Responsible for review shop drawing, measurement of the
Contract’s monthly estimate, review payment for price
adjustment and payment and preparing supplementary
agreement for variation work.
May 1998-January 1999 : Stc Co.,Ltd. (Contractor Company)
A Contractor in Steel Structure Fabrication
Project : PakseBridgeConstruction Project in Lao P.D.R.
Steel Form Work for Segment Casting
Client : VSL Thailand Co.,Ltd.(Sub Contractor)
[The Main Contractor is Shimizu Corporation ,Japan]
Position : Site Engineer
Job Description : Review of Shop drawings.Inspect of Steel Formwork Fabrication.
- Industry:
- Region: