Hi friends,
Today I did a simple testing take into account 3 activities and different calendars A (5WD) and B (7WD) and I had two different answers but, my question is, considering the CPM schedule we are limited to found a correct critical path according the calendar? What exactly happened?

Link file
https://we.tl/t-YVwrZDKvlf [2]
Best Regards,
Daniel Morais