I have read that you only get time for time that only the owner delayed the project, how can this be - because that would be compensatable. So time extensions are not granted for perfectly equal delays by owner and contractor? For example, I found this example: (seems crazy)
For example, if the contractor delayed the project by a week due to manpower issues, and the owner delayed work for two weeks reviewing submittals, the contractor could submit a request for a one-week extension.