Hi Cost Controllers,
I am using an earned value to track the progress and control costs, I am facing an issue which I do not understand how to manage it:
In the BOQ, I have hollow block and solid block with quantities and amount, I put the amount as PV.
In the actual work, the contractor cancelled the solid block and does not want to use it and will use hollow block instead for alll the building.
For example:
amount of hollow block is 75K
amount of solid block is 10k (which willl not be used) is 10K
These are considered PV
How can I deal with the EV for the solid block? I mean shall I enter a progress for it. considering that the progress for hollow block is 100%?