Hi
Is there any way to collapse summary tasks where OPC = 100% only?
My schedule contains a lot completed summary tasks so I don't want to show them in the view with entire content.
I can do this manually but looking for more convienient way.
Summary Tasks where OPC is under 100% should not be touched and be visible with all tasks underneath.
Something like below:

Thanks in advance!