Casino Fit Out - Delay Analysis (Time Impact Analysis) in support of the Contractors EoT claim and subsequent adjudication.
Shopping Centre Demolition - Delay Analysis (As Planned v as Built) in support of EoT and delay and disruption claims.
Gas Processing Plant - Delay Analysis (As Planned v As Built) in support of EoT and delay and disruption claim.
Police Federation Headquarters Construction – Sourcing contemporaneous records for Delay Analysis support of an EoT Claim (Time Impact Analysis)