Snr LEAD TENDER PLANNER David Adamson Group Ltd, UK Feb 2013 – May 2013
Selected to work in a tender planning capacity on a FIDIC contract project for KCC Hotel, Convention Centre, IT Park with a value of $200 m. Accountability was held for supporting a successful tender process
- Ascertained that relevant tender information was received and expertly assessed construction quantities and assigned output rates to produce tender durations with established effective timeframe for delivery.
- Identified planning conditions/client requirements and drafted construction programme, with full scope of works.