How do i get the duration to show just whole numbers e.g. 15w not 14.8w
The project is Mon to Fri 9-5pm.
I need to show the completion date as a friday not a sunday but still have the week as a whole number.
I have Sat & Sun as none working days in the project calendar.
Some tasks it works and some it doesn't and i can't undersatand why.
Please help :-)
Thanks