I'm working with a contractor who has just reciently changed the remaining duration on a few un-statused activites in the latest update. This is based on the USACE schedule requirement:
3.3.13 Original Durations
Activity Original Durations (OD) shall be reasonable to perform the work
item. OD changes are prohibited unless justification is provided to
and approved by the Contracting Officer.
An issue or argument has come up between me my colleague about which is correct when the plan has changed. I will not state my thought here.
Thanks