When I import an MS project file, the duration of the activities are divided by 3.
For example an actitivity has in MS Project a duration of 20 days and after import in PRA only 7 days.
I tried to change the import parameters and match the number of hours per day, but nothing changed.
Anyone familiar with this problem?