Hello,
The owner is requesting a schedule that has an "access" resource assigned to each activity, but several activities will be performed from the same "access" concurrently in the same location.
We have a travelling scaffold system from which eight schedule activities will be performed more or less concurrently in a 10 WD cycle.
How would you go about assigning a this single scaffold as a resource to multiple activities that will be using it in the same location concurrently?
Thanks for any ideas!