START Date:
August, 2012
END Date:
January, 2013 CALIBRE GLOBAL PTY LTD: Senior Planner – Brockman 4 Phase III FEED/Koodaideri Bid-Tender/Yandi Engineering/Turee Syncline – Projects ranging from AUD$80mm to AUD$500mm.
- Construction of a number of Projects for Rio Tinto’s proposed expansion of the Brockman 4 mine site using Primavera 6.7
- Delivering schedules at PES/DES L2 and L3 levels, maintenance & reporting of detailed execution plans to Levels 5/6.
- EPCM project reporting, e.g. Critical Path, Near-Critical Path, Total Float, EVM, SPI, CPI.
- Weekly/Monthly report outs & meetings – internal and ‘All-Party’.
- Assessment of 3rd Party schedules for progress as well as ‘work interface dependency’ plans.
- Develop the Koodaideri Bid/Tender plan from outline Contract & SoW (Scope of Work) – EPC.
- Measurement of programme against Contract.
Experience Hours (Planning & Scheduling):
650
Experience Hours (Forensic Analysis):
100