I have a preliminary schedule with no actuals from a contractor that I discovered has a critical or longest path made up of 16 multiple float paths base on free float. Most of the float paths are 1 or 2 activities. There are only 2 calendars used a 5 day and a 7 day. the 5 day calendar is used in all activities with exception of 5 activities. It only has one finish on or before constraint at project complete milestone and the NTP start milestone is on the data date. The total float is zero.
What is everyones opinion on this as far as analysis
Thanks
Patrick