Hello,
In my project I've "revised baseline" Dated 31-05-2017 and "recovery schedule" Dated 20-01-2018, updates are applied on the recovery schedule. Now, I've few change orders that I need to study thier impact and decide the EOT the Contractor deserves.
which one should I use and why, the revised baseline or the recovery schedule?
Clarification: the "recovery schedule" has the same end date and budget of the "revised baseline".
Thanks
A. AbdRabou.