Hello there!
I am using MSP 2016 and I have a doubt. As shown in the attached image, for the task name - Define, the duration is One day and it is showing a start date of 01/03/16 & 02/03/16 as finish date. Ok fine. In the Task Usage sheet - the work has been divided into 2 days with 4h work in each day. Why ?? Why not 8h in a single day?
I went to Options - Schedule and found out that the default start time is 8:00 AM with end time as 17:00. Hours per day is 8 (Standard Calendar).
The cost is fine on the Cost Sheet which is obvious as the total work hours is still 8hrs