Planner, CNE Invest Cernavoda
Project: Cernavoda Nuclear Power Plant Unit2, Client: CNE Invest Cernavoda
Job specific tasks:
Integrated time schedules per rooms(by discipline :civil, mechanic and electric activities, and by phase: engineering, procurement, erection) in order to ensure identification of any impact of critical activities to contractual milestones and commissioning program/turnover package.
Time schedule issuing for cooling system, moderator system, spent fuel system, main steam system, stand-by diesel generator.
Progress Reports on weekly / monthly basis
Critical path analysis and float management
Ensured interface with Procurement and Commissioning phases