Hi, how could i solve my problem on how to correct my earned value cost calculation on my updated Schedule in P6. Example of incorrect earned value cost is 2500USD instead of 6500USD at 100% Physical % Completed. Is there any way to resolve this issue? Is there any settings needs to fix in P6 v8.2? Thank you in advance.