Hi all,
I want the know how to update my P6 schedule based on activities original duration- project actual % complete. so i can compare it later to the Master baseline, i've tried project (Duration % Complete). but it doesnt seem to be accurate.
Note : i meant project overall actual progress.
thanks in advance.